The following is an annotated regulatory site history:

  • On July 8, 1999, a release of petroleum was identified at the property based on elevated PID readings obtained from soils stockpiled at the site. The soil stockpile had been generated from the removal of six (6) USTs in May of 1999.
  • On September 5, 1999, oral notification was provided to the MADEP by Subsurface Remediation Technologies, Inc. (SRT). The MADEP assigned Release Tracking Number (RTN) 3-18598. The MADEP issued a Notice of Responsibility to Bossi Realty Trust on November 19, 1999.
  • On November 7, 2000, the MADEP issued a Notice of Noncompliance (NON) to Bossi Realty Trust for failure to submit a Release Notification Form (RNF), an Immediate Response Action (IRA) Status Report, and a Response Action Outcome (RAO) Statement or Tier Classification.
  • On December 18, 2000, Bossi Realty Trust submitted an RNF and an IRA Plan in accordance with 310 CMR 40.0330 and 40.0424.
  • On April 4, 2001, Bossi Realty Trust submitted an IRA Completion Statement, Phase I Initial Site Investigation Report, and Tier 2 Classification based on a Numerical Ranking Scoresheet total of 138 in accordance with 310 CMR 40.0427, 40.0480, and 40.0500.
  • On May 24, 2004, the MADEP issued a Notice of NON for failure to complete and file a Phase II
    Report, a Phase III Remedial Action Plan and a Phase IV Plan within three years of the Tier II Classification.
  • On January 24, 2005, REMSERV, Inc. submitted a Phase II Scope of Work along with a schedule for implementing the Phase II, the Phase III Feasibility Analysis, the Phase IV Remedial Implementation Plan and the Phase IV Completion Statement for achieving a Remedy Operation Status or Response Action Outcome.
  • On March 14, 2005, the MADEP issued an Administrative Consent Order & Penalty (ACOP) (ACOP-NE-04-3A027) due to prior violations and the failure to submit a Phase II Report, a Phase III Remedial Action Plan, and/or a Phase IV Remedy Implementation Plan by required deadlines.
  • On May 6, 2005 Bossi Realty Trust submitted a Phase II Comprehensive Site Assessment Completion Statement.
  • On July 11, 2005 Bossi Realty Trust submitted a Phase III Remedial Action Plan.
  • On August 16, 2007 Bossi Realty Trust submitted a Phase IV Remedy Implementation Plan.
  • On June 26, 2012 Bossi Realty Trust submitted a Class C-2 Response Action Outcome and Tier II Extension.
  • On June 27, 2013 Bossi Realty Trust submitted a Post Class C-2 Response Action Outcome Status Report and a Tier II Extension.